ISTQB_TEST MANAGEMENT_ The Test Process_1.1.3 Test Completion

 Test completion activities ensure the test phase is formally closed and lessons are captured for future improvements.

  • Finalizing and Archiving Testware:

    • All test artifacts such as test cases, test data, logs, and scripts are archived.

    • These may be reused or audited in the future.

  • Test Completion Reporting:

    • Summary report showing what was planned vs. achieved.

    • Includes metrics, defect stats, coverage, and remaining risks.

  • Environment Cleanup:

    • Restore test environments, remove temporary data, release resources.

  • Open Defects and Handover:

    • Ensure all known defects are documented and handed over to maintenance/support.

  • Lessons Learned & Process Improvement:

    • Conduct retrospectives or post-mortems.

    • Document challenges, successes, and improvement suggestions.

Mock Questions: 1.1.3 – Test Completion

Question 1 (K1 - Remember)

Which of the following is NOT a typical activity in the test completion phase?

  • A. Finalizing and archiving testware

  • B. Preparing the test completion report

  • C. Executing final regression tests

  • D. Documenting lessons learned
    ✔️ Answer: C

Question 2 (K2 - Understand)

Why is it important to archive testware during test completion?

  • A. To allow immediate reuse without review

  • B. To eliminate the need for future planning

  • C. To support audits, maintenance, and knowledge transfer

  • D. To ensure all tests pass
    ✔️ Answer: C

Question 3 (K2 - Understand)

Which of the following best describes the purpose of a test completion report?

  • A. To list test scripts that were automated

  • B. To compare actual results with planned objectives and summarize outcomes

  • C. To evaluate the UI experience for end users

  • D. To measure developer productivity
    ✔️ Answer: B

Question 4 (K3 - Apply)

A project has completed testing but has several low-priority open defects. What should the Test Manager do before test closure?

  • A. Wait until all defects are fixed

  • B. Reject the build for release

  • C. Communicate open defect status and obtain stakeholder approval

  • D. Delete low-priority defects to clean up the tracker
    ✔️ Answer: C

Question 5 (K2 - Understand)

Which of the following is MOST useful for identifying test process improvement opportunities?

  • A. Test execution logs

  • B. Lessons learned during retrospectives

  • C. Release notes from the development team

  • D. User interface feedback
    ✔️ Answer: B

No comments:

Post a Comment

Lets Start...............

Cypress

Syllabus Q & A Set -1 Q & A Set -2