📌 Success Metrics of Risk-Based Testing
Metric Question | Purpose |
---|---|
Were relevant stakeholders involved in risk analysis? | Ensures right people contributed to risk identification |
Was stakeholder involvement appropriate? | Confirms quality and relevance of stakeholder input |
Were critical production incidents resolved? | Measures how well post-deployment risks were managed |
Were most high-priority defects found early? | Validates early risk mitigation via testing |
Could the test team explain results in terms of risk? | Shows alignment of test reporting with risk framework |
Did skipped tests have lower risk than executed tests? | Confirms correct prioritization during test planning |
⚠️ Difficulties in Risk-Based Testing
Issue | Cause | Solution |
---|---|---|
Difficulty in assessing risk | Estimating impact/likelihood is hard | Use historical data and stakeholder assessment |
Keen beginnings | Initial enthusiasm fades under pressure | Maintain momentum via regular risk monitoring/reporting |
Déjà vu | Same risks repeated = complacency | Involve right people, prioritize only important risks |
Key risks missed | Inexperienced/inappropriate participants | Involve trained, experienced stakeholders |
Stakeholder churn | Change in stakeholders, emergence of new risks | Treat risk analysis as iterative, not one-time activity |
🧠 2. Visual Mind Map for Revision
Mind Map 1: Success Metrics of RBT
Mind Map 2: Difficulties & Solutions
🎯 3. Scenario-Based Multiple-Choice Questions (MCQs)
✅ Question 1 (K2): Understanding Risk-Based Testing Metrics
Scenario: A test manager reports that all high-priority defects were found during the initial test cycles. Also, skipped test cases had low associated risk.
Which of the following is MOST likely true?
A. Test team followed test automation best practices
B. Risk-based testing approach was successful
C. Stakeholders had no involvement in test planning
D. There was no need for exploratory testing
Correct Answer: B
✅ Question 2 (K3): Evaluating a Situation
Scenario: In a financial app release, critical defects escaped into production despite performing risk analysis. Upon review, it was found that only junior testers participated in the risk analysis sessions.
What is the root cause and the BEST solution?
A. Testers weren’t trained – assign more exploratory sessions
B. Too much testing was skipped – test more
C. Key risks were missed – involve appropriate, trained stakeholders
D. Metrics were ignored – track more KPIs
Correct Answer: C
✅ Question 3 (K4): Applying Process Improvement
Scenario: The QA lead observes that the same risks appear in every project and testers no longer treat them seriously.
Which action should the test manager take to address this issue?
A. Rotate team members to reduce bias
B. Ignore such risks since they are predictable
C. Involve the right people and prioritize only meaningful risks
D. Reuse the same risk register across all projects
Correct Answer: C
Q1: (K2) Which of the following is a valid success metric of risk-based testing?
A. Test design coverage was above 85%
B. Stakeholders could understand test results in terms of risk
C. Test automation reduced execution time
D. All critical test cases were passed
Answer: B
Q2: (K3) Risk-based testing was implemented, but many critical defects were found after release. What is MOST likely the cause?
A. Defect priority was incorrectly marked
B. Testers skipped integration testing
C. Inexperienced people did risk analysis
D. Automated tests weren’t used
Answer: C
Q3: (K3) The team has been using the same risk list for the last five releases. What issue might arise?
A. Test data may become outdated
B. Developers may lose trust
C. Team may become complacent toward those risks
D. Risk register might become too short
Answer: C
Q4: (K4) A test manager wants to avoid stakeholder churn affecting the risk-based testing. What is the BEST approach?
A. Finalize all risks before test execution begins
B. Document risks in the test strategy only
C. Make risk analysis an iterative process
D. Keep test plans generic to accommodate all risks
Answer: C
Q5: (K3) A team found that skipped tests had higher risk levels than executed ones. What does this indicate?
A. Good test prioritization
B. Improper risk-based selection of test cases
C. Efficient automation strategy
D. Success in exploratory testing
Answer: B
No comments:
Post a Comment