Who are considered developers in a Scrum Team?
- A. Stakeholders
- B. Product Owner
- C. Scrum Master
- D. Developers
- Answer: D. Developers
- Explanation: Developers are the people in the Scrum Team committed to creating any aspect of a usable Increment each Sprint.
What are developers in a Scrum Team committed to creating each Sprint?
- A. Product Backlog
- B. Usable Increment
- C. Roadmap
- D. Sprint Review
- Answer: B. Usable Increment
- Explanation: Developers are committed to creating a usable Increment each Sprint.
Which of the following responsibilities are developers always accountable for? (Select all that apply)
- A. Creating a plan for the Sprint, the Sprint Backlog
- B. Instilling quality by adhering to a Definition of Done
- C. Setting the release date for the product
- D. Adapting their plan each day toward the Sprint Goal
- E. Holding each other accountable as professionals
- F. Managing the budget for the project
- Answers: A, B, D, E
- Explanation:
- A. Developers create a plan for the Sprint, the Sprint Backlog.
- B. Developers instill quality by adhering to a Definition of Done.
- D. Developers adapt their plan each day toward the Sprint Goal.
- E. Developers hold each other accountable as professionals.
True or False: The specific skills needed by the Developers are always the same regardless of the domain of work.
- A. True
- B. False
- Answer: B. False
- Explanation: The specific skills needed by the Developers are often broad and will vary with the domain of work.
Who is responsible for creating a plan for the Sprint, known as the Sprint Backlog?
- A. Product Owner
- B. Scrum Master
- C. Developers
- D. Stakeholders
- Answer: C. Developers
- Explanation: Developers are responsible for creating a plan for the Sprint, which is known as the Sprint Backlog.
What quality must developers instill by adhering to a specific standard?
- A. Budget adherence
- B. Roadmap alignment
- C. Definition of Done
- D. Market requirements
- Answer: C. Definition of Done
- Explanation: Developers must instill quality by adhering to the Definition of Done.
How often should developers adapt their plan toward the Sprint Goal?
- A. Weekly
- B. Monthly
- C. Daily
- D. Annually
- Answer: C. Daily
- Explanation: Developers should adapt their plan each day toward the Sprint Goal.
Who holds the developers accountable as professionals?
- A. Product Owner
- B. Scrum Master
- C. Stakeholders
- D. Developers themselves
- Answer: D. Developers themselves
- Explanation: Developers hold each other accountable as professionals.
True or False: Developers are responsible for managing the project's budget.
- A. True
- B. False
- Answer: B. False
- Explanation: Managing the project's budget is not listed as one of the developers' responsibilities in Scrum.
Which document do developers create to outline their work for the Sprint?
- A. Product Backlog
- B. Sprint Backlog
- C. Project Charter
- D. Release Plan
- Answer: B. Sprint Backlog
- Explanation: Developers create the Sprint Backlog to outline their work for the Sprint.